What Would the Southwest Connection Cost?

  • Fight FM150
  • Jul 23
  • 6 min read

Updated: Jul 23

A plain-language cost guide for Dripping Springs / Hays County residents ·

~2026 dollars · construction not funded

$300M

Mid all-in (8.5 mi)

$164–$505M

Planning range

$35M

Per mile (mid)

Not funded

Construction status

This is an estimate — and design ≠ construction

The ~$300M mid figure is a public construction yardstick from local comps and TxDOT bridge costs. It will move when engineers lock alignment, spans, and ROW. Construction is still not funded. What is funded so far is design: about $0.75M (2019 Friese study) plus a $2.99M Structurepoint design contract (Dec 2025) — not building the road.

The short answer

Building the full preliminary corridor from US 290 to RM 12 — about 8.5 miles of new four-lane divided road with bike/ped space, multiple Onion Creek crossings, and roundabouts at major local roads — lands near $300M mid (~$35M per mile), with a planning range of about $164–$505M. That is in the same ballpark as Hays County’s Darden Hill Phase 2 (1.7 mi of four-lane divided at $51.8M all-in, or ~$30.5M per mile).

Design already under contract

These are real professional-services contracts. They pay for studies and plans — not

asphalt, bridges, or right-of-way acquisition for construction.

Contract

Amount

When

What it covers

K Friese + Associates

$750,000

Dec 2019

Preliminary engineering + public involvement (RM 12 → US 290 study / ~20% design era)

American Structurepoint

$2,986,101

Dec 2025

Additional planning & design, US 290 → RM 12 (Pct 3 & 4); schematic through PS&E via work authorizations

Friese: Hays County minutes 2019-12-10 (RM 150 Extension PSA). Structurepoint: Dec 16 2025 agenda packet compensation cap (selected Nov 18 2025). County project page still shows ~$4M design framing; Community Impact has cited ~$1.44M for the 2.4 mi Precinct 4 slice — neither is a construction OPCC.

Corridor map and elevation profile

Crossings and junctions (with planning cost)

ID

Mile

Elev (ft)

Span (ft)

Mid $M

Type

Name

R1

0.00

1093

9.0

Roundabout

RM 12 / RM 150

B1

0.29

1037

520

7.0

Bridge

Onion Creek main floodplain

B2

1.08

1086

410

5.7

Bridge

Onion Creek trib / east draw

R2

2.41

1228

4.0

Roundabout

Mt Gainor Rd

B3

2.48

1183

260

4.0

Bridge

Valley west of Mt Gainor

B4

4.46

1205

260

4.0

Bridge

Major valley

B5

5.22

1194

490

6.9

Bridge

Major valley

R3

6.19

1212

4.0

Roundabout

Pursley Rd

B6

6.24

1182

260

4.0

Bridge

Major valley

B7

7.61

1215

200

3.0

Bridge

Draw floodplain ~200 ft

R4

8.25

1313

4.0

Roundabout

Creek Rd / RM 165

Spans from DEM valley width (+15 ft rise mid); cost = structure + approaches at TxDOT FY2025 ~$135/sf × 90 ft deck. B2 mid treats half the broad valley as embankment. R1 (~$9M) is a separate county project — not inside the $300M corridor total. R2–R4 share the corridor intersections line (~$4M each).

Baseline 1 — the road

Cleanest local comparison: Darden Hill / CR 162 Phase 2 (Sawyer Ranch roundabout → RM 1826) — 1.7 mi four-lane divided at $51.793M all-in (const + utilities + ROW + design + CEI), or about $30.5M per mile.

Scaling that rate to 8.55 mi ≈ $260.7M for roadway-class work. Our full-project mid (~$300M, ~$35M/mi) sits a little higher — expected for a greenfield alignment with more bridges, recharge-zone drainage, and new right-of-way. Darden is largely a widening; this corridor is mostly new road across draws and floodplain.

Baseline 2 — bridges

Instead of one guess for every crossing, valley width is measured on the 10 m DEM profile (how far ground stays within ~15 ft of the local low). Cost uses TxDOT FY2025 ~$135/sf (unit-cost PDF), a ~90 ft deck, and a small approach allowance. B2’s broad bowl is half bridge / half fill in the mid case.

Majors B1–B6 mid sum ~$31.4M · B7 in minor structures · Source: DEM profile spans × TxDOT $/sf

Local bridge comp

Setting

Public $

Why it matters

Creek Rd (CR 190) Onion Creek

2-lane off-system replacement, DS

~$1.5–1.6M

Floor for a modest span — nearer B3/B4/B6 than B1

Cole Springs Rd Onion Creek (Buda)

New crossing + developer package

~$7.6M

Same order as B1 mid (~$7M)

Baseline 3 — roundabouts

County preference has been roundabouts at major local roads. The east-end gateway — RM 150 at RM 12 — is already a multi-million-dollar project by itself (~$5M county CO + ~$3.8–4.2M CAMPO; published figures vary about $5–9M). Corridor RAs use that scale as a planning check.

ID

Crossing

Mid $M

In corridor total?

R1

RM 12 / RM 150

~$9.0M

No — separate project

R2

Mt Gainor Rd

~$4.0M

Yes — share of ~$12M RA / tie-in line

R3

Pursley Rd

~$4.0M

Yes — share of ~$12M RA / tie-in line

R4

Creek Rd / RM 165

~$4.0M

Yes — share of ~$12M RA / tie-in line

R1 mid ~$9M from published RM12/150 package (not added again into the $300M corridor total). R2–R4 mid ~$4M each (= $12M corridor intersections line ÷ 3); R4 also covers the US 290 tie-in.

Putting the pieces together

Hard construction ~$180.4M plus soft costs / ROW / risk ~$119.1M → ~$300M mid (~$35M per mile). Planning range about $164–$505M.

Bucket

Mid ~$M

Everyday comparison

Roadway + drainage + paving + earthwork + bike/ped + util + mob.

131

Darden Hill × length, adjusted for new alignment

Bridges & large culverts

38

Profile spans; B2 half-fill; B1/B5 long

Intersections (corridor RAs)

12

Below full RM12/150 cemetery-shift package each

Contingency + design + CEI + ROW + env

119

~195 ac net take + planning contingency

All-in mid

300

~$35M per mile

Line-item planning estimate (mid $M)

Road projects usually call this an engineer’s line-item estimate or OPCC — not a manufacturing “BOM.” Each row is a planning allowance; the anchor is a public dollar figure (unit bid, local project, or % of construction) that sets the scale.

Hard construction (~$180.4M)

Category

Mid $M

Anchor

Earthwork / grading / rock

20.6

Pavement structure (4 lanes + median + shoulders)

44.5

Drainage, storm sewer, water-quality BMPs

32.0

Major bridges (6 crossings, profile spans)

31.4

Minor bridges / large box culverts

6.5

Shared-use / bike-ped facilities

7.8

Signing, striping, signals/lighting

6.4

Intersections & roundabouts

12.0

Utilities / prep ROW / fencing

8.9

Mobilization / traffic control / SWPPP

10.3

Soft costs / ROW / risk (~$119.1M)

Confidence

Planning accuracy is roughly ±35–50% until Structurepoint schematic design and surveyed ROW exist. Costs follow the 2021 preliminary centerline; a shifted preferred alignment changes bridges and parcels. R1 is separate — do not double-count it into the corridor mid. Combined design fees (~$3.7M Friese + Structurepoint) are not a construction OPCC.

Sources

Hays County minutes — Dec 10 2019 — K Friese PSA $750,000 (RM 150 Extension / SW Connection study)

Hays County agenda packet — Dec 16 2025 — American Structurepoint design compensation cap $2,986,101

Darden Hill Phase 2 — $51.793M; 1.7 mi; const + util + ROW + design + CEI

RM 150 at RM 12 Roundabout — ~$5–9M published / CAMPO share · County SW Connection page (~$4M design framing)

TxDOT FY 2025 Bridge Unit Costs — ~$135.29/sf · Creek Rd CR 190 (~$1.5–1.6M) · Cole Springs, Buda (~$7.6M) · USGS 3DEP 1 m DEM · 2021 centerline

Independent planning-level estimate for public discussion. Not a Hays County engineer’s estimate, OPCC, or bid.

 
 